Esther Checklist Management.

Completed Actions in Shot, Report Id: 318

ID Order Date/Time Action Status Resp
3 10 2026-04-09 09:41:24.454812 Ensure gas supplies (for the Driver and the Test Gases) are OFF V CE
4 20 2026-04-09 09:41:35.462342 Ensure mechanical operator to wear proper PPE V CE
59 30 2026-04-09 09:41:52.390983 Turn ON water cooling pump. Check water running inside closed circuit. V CE
127 35 2026-04-09 09:42:31.513526 OPEN pneumatic air valves V CE
5 40 2026-04-09 09:42:41.141968 Ensure every safety systems are ON and OK (fire alarm, emergency lighting, gas detection…) V CE
6 50 2026-04-09 09:43:55.781047 Ensure UPS of control room is ON, supplying computers, control panel and gas detection system. Ensure that the PLC control systems (in the control room and the experimental hall rack) are ON V CE
7 60 2026-04-09 09:44:04.361737 All doors to remain unlocked as normal for fire escape/access V CE
128 65 2026-04-09 09:44:12.111597 Place overhead crane in position to lift CT V CE
8 70 2026-04-09 09:46:02.860137 Turn ON necessary electrical equipment (computers, oscilloscopes, etc...) V RE
121 80 2026-04-09 09:46:53.028622 Ensure that all EPICS IOC systems are running. Start CSS Archive Engine. See <a href="https://github.com/ipfn-hpl/esther-ops#epics-control-system" target="_blank">Link</a> V RE
1 80 2026-04-09 09:47:28.067438 Initiate Shot - Assert Start of Day V RE
9 90 2026-04-09 09:47:41.305767 Make a realistic assessment on whether the test can be completed within the imparted time (e. g. if it is 16:00 maybe it is not a good idea to start a test if you plan to leave at 17:00). V RE
31 10 2026-04-09 10:01:55.746182 Verify that all other general and subsystem safety conditions are met (see Master checklist) V CE
33 20 2026-04-09 10:02:07.091552 Disable electrical supplies to all non-ATEX electrical equipment in the ATEX area V CE
34 30 2026-04-09 10:03:35.478284 Ensure all doors and gate from experimental hall are CLOSED V CE
35 40 2026-04-09 10:03:49.015053 Place the recoil dampening bags (Aluminium bullet bags) in contact with the rear of the combustion chamber. Ensure these do not block the laser optical path. V CE
37 50 2026-04-09 10:04:47.330983 Check for lack of human presence in the gas compressor room and CLOSE door V CE
38 60 2026-04-09 10:05:11.258075 Leave experimental hall and make visual check and audible warning V CE
41 70 2026-04-09 10:05:37.934438 CLOSE control room/lab door V CE
42 80 2026-04-09 10:08:51.159220 OPEN gas storage doors; Turn ON gas supplies; CLOSE and LOCK gas storage doors V CE
129 155 2026-04-09 10:08:57.558564 Lift CT with overhead crane V CE
43 90 2026-04-09 10:35:17.412339 Log in to control console V RE
111 100 2026-04-09 10:36:06.355563 Check that Bottle pressure are compatible with planned shot V RE
10 110 2026-04-09 10:41:48.117290 Agree and sign the global shot setup parameters sheet (driver, compression tube, and test section gas fillings, vacuum parameters, diagnostics, etc…). Ensure parameters are nominal for shot and all equipment is in good condition. Two signatures are needed in the compliance form. V CE
30 100 2026-04-09 10:46:06.631314 Agree and sign the global shot setup parameters sheet (driver, compression tube, and test section gas fillings, vacuum parameters, diagnostics, etc…). Ensure parameters are nominal for shot and all equipment is in good condition. Two signatures are needed in the compliance form. V RE
29 130 2026-04-09 10:46:10.810728 Ensure that at least one researcher and the chief engineer are present during the test, one to remain in control room throughout. V RE
110 110 2026-04-09 10:48:35.138443 Set Bottle low-pressure alarms according to states V RE
44 120 2026-04-09 10:48:38.808013 Enter normalized parameters from log sheet V RE
11 120 2026-04-09 10:50:19.440345 Ensure that at least one researcher and the chief engineer are present during the test, one to remain in control room throughout. V CE
12 150 2026-04-09 10:50:32.418444 Ensure CC, CT and ST are clean. Perform hardware inspection. Place diaphragms in CC-CT, CT-ST, and ST-DT sections. V CE
130 155 2026-04-09 10:50:37.703822 Lift CT with overhead crane V CE
13 160 2026-04-09 10:50:54.816782 Ensure there is no leaks of hydraulic fluid. Undertake hydraulic closure procedure for the CC-CT, CT-ST, and ST-DT sections (See Procedimento HPL-012020). V CE
58 10 2026-04-09 10:52:06.535381 Verify that all other general and subsystem safety conditions are met (see Master checklist) V CE
125 85 2026-04-09 10:52:16.334677 Close DT Bottom purge Valve V CE
126 177 2026-04-09 10:53:13.611369 Set DT Output Valve to Shot Position V CE
45 130 2026-04-09 10:55:25.311108 Turn on Kistler & start archive engine V RE
107 140 2026-04-09 10:55:28.635888 Fully open purge valve v701 V RE
108 150 2026-04-09 10:55:31.042603 Start CC Purging Sequence V RE
32 20 2026-04-09 10:56:20.454329 Verify that all the sections of the shock-tube (CC-CT, CT-ST, ST-DT) are CLOSED with a diaphragm inside, and pressurized to the preset values in each station. Report the hydraulic pressure in each section. V RE
60 30 2026-04-09 10:56:26.067871 Turn ON the two turbomolecular pump fans V RE
61 40 2026-04-09 10:56:33.135562 Turn ON the two turbomolecular pump controllers and ensure that the pumps are levitating nominally without any error messages ATT RE
62 50 2026-04-09 10:56:48.091546 Ensure that the two ST gate valves are OPEN (if p_ST=1bar) and that the two mechanical arms are in the OPEN position V RE
63 60 2026-04-09 10:57:43.894889 Ensure that all the pressure sensors (1x CT, 2x ST, and 2x DT) are ON (turn then ON when required) ATT RE
64 70 2026-04-09 10:57:52.774140 Ensure that the CT ball valve is in the pump <-> CT section position and that the DT ball valve is in the pump <-> DT section position V RE
65 80 2026-04-09 10:58:01.884160 Ensure that all the control software is ON (boot it as needed) and that the archive engine is active V RE
66 90 2026-04-09 10:58:04.608583 Turn ON the DT primary pump V RE
67 100 2026-04-09 10:58:08.787724 After XXX seconds turn ON the CT primary pump V RE
69 110 2026-04-09 10:58:22.443727 After XXX seconds turn ON the ST primary pump. If gate valves are still CLOSED, open them after 1 min. V RE
70 120 2026-04-09 11:00:01.314168 After XXX seconds, ensure that the CT massflow controller is in the CLOSED position, then switch the CT ball valve to the gas-filling system <-> CT section position, wait YYY seconds, and switch back to the pump <-> CT section position, to purge the CT gas lines downstream of the massflow controller V RE
88 140 2026-04-09 11:13:22.593629 Check that the laser is aligned with the optical port. Open CC if needed. V RE
14 170 2026-04-09 11:13:26.192559 Initiate Vacuum Procedure. V RE
15 180 2026-04-09 11:13:30.928962 After the necessary time (experiment-dependent), initiate Combustion Driver procedure. V RE
71 130 2026-04-09 11:14:08.292545 After pressure in the ST section falls in the 1e-1 mbar range, start the acceleration of both ST turbomolecular pumps V RE
84 10 2026-04-09 11:14:51.466759 Verify that all other general and subsystem safety conditions are met (see Master checklist) V CE
131 13 2026-04-09 11:15:00.924366 Open He Bottle of Gas Injection V CE
104 140 2026-04-09 11:32:24.622850 (Optional) Once required pressure is met in ST section, CLOSE gate valves, wait 5min, then OPEN gate valves. V RE
105 150 2026-04-09 11:32:51.306766 (Optional) Once required pressure is met in CT section, switch pneumatic valve from CT <-> Pump to CT <-> GFS, wait 5min, then switch back. V RE
106 160 2026-04-09 11:32:59.040352 (Optional) Once required pressure is met in DT section, switch pneumatic valve from DT <-> Pump to DT <-> Purge, wait 5min, then switch back. V RE
109 160 2026-04-09 12:05:05.575952 Fully close valve V701 then open half turn V RE
46 170 2026-04-09 12:05:08.308663 Initiate filling sequence V RE
89 15 2026-04-09 12:15:08.127603 Fill/check the parameters for CT & ST masscontrollers V RE
116 100 2026-04-09 12:48:10.290652 Verify subsystem safety conditions for Shot V CE
47 180 2026-04-09 12:49:16.396696 Record the partial filling pressures V RE
48 190 2026-04-09 12:49:20.128720 Check that fill is nominal and that the correct final pressure has been reached V RE
132 110 2026-04-09 12:49:29.089614 Close He Bottle of Gas Injection V CE
49 200 2026-04-09 12:49:35.797974 Check that CC is properly insulated from the piping system (Maximator valves closed) V RE
86 10 2026-04-09 12:50:43.948838 Verify that all other general and subsystem safety conditions are met (see Master checklist) V CE
72 170 2026-04-09 12:51:00.646580 When the required pressures in all the sections (CT, ST, DT) are met, initiate braking of Turbo Pumps. V RE
92 173 2026-04-09 12:51:13.919233 Switch pneumatic valve from DT <-> Pump to CT <-> Exhaust V RE
93 175 2026-04-09 12:51:23.255653 Turn off DT Primary pump V RE
90 180 2026-04-09 12:51:27.581854 Switch pneumatic valve from CT <-> Pump to CT <-> GFS V RE
91 190 2026-04-09 12:51:31.822339 Turn off CT Primary pump and switch to Test Gases checklist. V RE
96 30 2026-04-09 12:51:42.277328 Perform Test Gases filling procedure for CT. Verify that the correct filling pressures have been reached. Resume Vacuum checklist. V RE
95 220 2026-04-09 13:00:02.368133 When both turbos < 5,000-10,000 RPM (TBC) close gate valves and switch to Test Gases checklist. V RE
16 190 2026-04-09 13:00:14.697934 After Vacuum procedure concludes, initiate Test Gas Filling procedure. V RE
97 40 2026-04-09 13:25:19.395774 Perform Test Gases filling procedure for ST. Verify that the correct filling pressures have been reached. Resume Vacuum checklist. V RE
99 230 2026-04-09 13:25:30.570849 Close shock insulation plugs and check they are in their CLOSED position. V RE
100 240 2026-04-09 13:25:34.040731 Check that both turbo pumps are in levitation position. Turn off pumps ventilation and controller (Optional). V RE
101 250 2026-04-09 13:25:35.939746 Shut down primary ST pump V RE
102 260 2026-04-09 13:25:38.565804 Manually pressurize the vacuum lines between the turbopumps and the primary pump. V RE
83 270 2026-04-09 13:26:02.104499 Verify subsystem safety conditions for Shot V CE
50 210 2026-04-09 13:26:07.071427 Ensure that the Vacuum and test gas filling procedures have concluded successfully and that the shock-detection and diagnostic systems are ready for recording the shot and waiting for the triggers recorded at shock wave passage V RE
51 220 2026-04-09 13:26:16.232013 Prepare the Kistler gauge system to record the ignition sequence; program all the necessary triggers (oscilloscopes, acquisition cards, etc...) V RE
36 230 2026-04-09 13:26:19.722181 Turn ON laser ignition system V RE
117 195 2026-04-09 13:26:51.657535 Verify General and Subsystem safety conditions for ignition V CE
118 235 2026-04-09 13:27:00.024931 ARM Ignition Laser See <a href="https://github.com/ipfn-hpl/esther-ops/tree/main/pulse-sequence" target="_blank">Link</a> V RE
52 240 2026-04-09 13:52:26.027138 Fire the laser ignition system V RE
82 310 2026-04-09 14:09:16.021657 Turn OFF the water cooling circuit pump V CE
53 245 2026-04-09 14:09:36.311926 Record full pressures and volumes on log V RE
122 247 2026-04-09 14:09:38.983213 Set laser flash to Standby V RE
55 310 2026-04-09 14:09:45.808341 Open gas storage doors; Turn OFF gas supplies; Close and lock gas storage doors V CE
112 250 2026-04-09 14:09:46.573568 If CC NOT ignited, start CC ABORT sequence to flush mixture NC RE
54 290 2026-04-09 14:09:50.182024 Set control system to idle V RE
17 200 2026-04-09 14:10:09.933145 After shot is concluded, ensure that all the relevant data (pressures, diagnostics, etc…) are recorded, and that pressure inside the chamber (measured in the Dump Tank station is around atmospheric pressure, accounting for the sensor noise. V RE
18 210 2026-04-09 14:10:13.397135 Allow for additional 5min wait time for safety reasons. V RE
19 230 2026-04-09 14:10:21.489997 Turn ON the ST primary pump to vent out any leftover Helium and Water Vapour. When pressure is lower than 100mbar, turn OFF the ST primary pump. NC RE
56 220 2026-04-09 14:10:53.990544 Enter lab and open doors. Perform a visual inspection V CE
20 240 2026-04-09 14:10:59.507880 Undertake hydraulic opening procedure (See Procedimento HPL-012020). V CE
124 245 2026-04-09 14:11:03.619501 Open CC/CT/ST/DT Sections V CE
21 250 2026-04-09 14:11:08.922398 Purge condensed water from the Dump Tank. V CE
22 260 2026-04-09 14:11:20.588944 Remove the burst-ed CC-CT, CT-ST, and ST-DT diaphragms. NC CE
23 270 2026-04-09 14:11:43.472872 Check mechanical parts for damage, record for future maintenance. V CE
24 290 2026-04-09 14:11:53.308956 Sign test report. End of test. V CE
28 280 2026-04-09 14:12:00.519526 Sign test report with this form attached. End of test. V RE
57 260 2026-04-09 14:12:22.105936 Turn OFF laser ignition system V CE
113 270 2026-04-09 14:12:33.914890 Remove the recoil dampening bags. V CE
115 300 2026-04-09 14:12:38.043496 Verify subsystem safety conditions V CE
123 300 2026-04-09 16:03:33.938426 If necessary perform End Of Day Checlists V RE
25 300 2026-04-09 16:13:55.815650 Turn OFF relevant electrical equipment (computers, oscilloscopes, etc…). V RE
26 320 2026-04-09 16:22:45.074351 General cross-check of the experimental hall, control room, and compressor room for any anomalies. V CE
103 330 2026-04-09 16:23:49.062357 Perform PostgreSQL dump and backup to NAS V RE